Crusher Duplication Bulk Earthworks at Wodgina Mine Site
PROJECT OVERVIEW
Mine Site Construction Services (MSCS) were contracted by Global Advanced Metals (GAM) to define Tailings boundaries on TSF2 using material won from the preparation of the ROM pad and tailings re-handling area.
CLIENT
Global Advanced Metals (GAM)
RESOURCE
Tantalum
LOCATION
Wodgina, WA (Approx. 100km south east of Port Hedland)
CONTRACT PERIOD
July 2011 to July 2012
Personnel Employed
70
+
Crusher Area & TSF2
388000
bcm
Roads
108000
bcm
ROM Base
67000
bcm
Skyway
321500
bcm
Plant Items Mobilised
50
+
Services Provided
– Define Tailings boundaries on TSF2 using material from the preparation of the ROM pad and tailings re-handling area
– Excavation and transport to the tails re-handling area and cap with approved material
– Import, place and compact select structural fill material from North Dump area to crusher pad area
– Construction of roads from base of pad area and around ROM pad
– Construction of Skyway and ROM pad access from haul road
– Mobilisation and Management of over 50 plant items