Dardanup Mine Site

CLIENT

Doral Mineral Sands (Iwatani Corporation Japan)

RESOURCE

Heavy Mineral Sands

CONTRACT PERIOD

October 2012 – May 2018

LOCATION

Burekup – Western Australia

CLIENT

MINING SERVICES PROJECT

Personnel Employed
50

+

Grade Banks Constructed
18

KMs

Iluka Dams Seeded & Fertilised
109

Ha

Disturbance to Rehabilitation Area
660.1

Ha

Material Quantity Ore & Overburden
10000000

bcm

PROJECT OVERVIEW

Mine Site Construction Services provided client Doral Mineral Sands Mining and Rehabilitation Services at the Dardanup Mineral Site between October 2012 and May 2018.

[Matt to assist with a summary overview of this project.Matt to assist with a summary overview of this project.Matt to assist with a summary overview of this project.Matt to assist with a summary overview of this project.Matt to assist with a summary overview of this project.]

SERVICES PROVIDED

  • Mining Operations 24/7 @ 365 days in low lying, high rain fall area of Western Australia.
  • ROM Feed Operations: 24/7 Year round double shift @ min feed rate of 400tph.
  • Rehabilitation of disturbance areas in conjunction with ongoing mining operations – “pit to pasture”.
  • Reinstatement of gazed main roads to Main road specification.
  • Reinstatement of Water Corporation irrigation channels.
  • Removal of Client plant and infrastructure.
  • Management of local DIDO workforce.
  • Daily production reporting and monitoring reportable to client.
  • Control of back fill area/s in conjunction with GPS aided equipment due to limited top soil balance
  • Low ground pressure equipment employed to place fill in existing tailing areas and that had initial cap of co-disposed fill in situ.
  • Dieback management of plant and equipment via Green Card status